Green Bay Road Reconstruction Project - Latest Updates
|
THE CONSTRUCTION SCHEDULE STARTING WEDNESDAY, NOVEMBER 11, HAS CHANGED: Wednesday, November 11:
Thursday, November 12:
Friday, November 13, Saturday November 14, & possibly the following week starting Monday, November 16:
Please use caution when traveling through the work zone, follow all traffic control personnel and signage, and allow additional travel time. For the latest construction updates, maps, and project information, visit lakebluff.org ***** PREVIOUS CONSTRUCTION SCHEDULE PUBLISHED 11/6: Green Bay Road Construction Updates: Phase 1 of the Green Bay Road Reconstruction is nearing completion. Saturday, November 7 Crews will continue landscaping and pouring concrete for sidewalk gaps. Monday, November 9 – Friday, November 13 On Monday, November 9, crews will continue cleaning the pavement, and place joint seal down the center of Green Bay Road on Tuesday, November 10. On Wednesday, November 11, crews will apply tack coat, a fresh oil, in the early morning, and pave the final layer of asphalt surface on Green Bay Road during the day. There will be flaggers on site to direct traffic through the work zone. Crews will also pave asphalt driveways and install new signs and pavement markings within the project site. Looking Ahead: Week of November 16 The project should wrap up any remaining punch list items and cleanup. Please use caution when traveling through the work zone, follow all traffic control personnel and signage, and allow additional travel time. For the latest construction updates, maps, and project information, visit lakebluff.org. Green Bay Road Construction Update - October 30, 2026 Phase 1 of the Green Bay Road Reconstruction is nearing completion. This project should be completed the week of November 9. There will be no work on Saturday, October 31. Enjoy Trick-or-Treating from 4pm – 7pm! Monday, November 2 – Saturday, November 7 Landscapers will begin to restore the parkway areas. The contractor will finish pouring concrete for any remaining sidewalk and curb & gutter. Utility frames will be adjusted in the new pavement to the final surface grade in preparation for paving the final layer of asphalt surface the week of November 9. Looking Ahead: Week of November 9 The contractor will pave the final layer of asphalt surface, and install signs with pavement markings to follow. Please use caution when traveling through the work zone, follow all traffic control personnel and signage, and allow additional travel time. For the latest construction updates, maps, and project information, visit lakebluff.org.
Green Bay Road Reconstruction Update: October 23, 2026. This project is expected to be complete the week beginning November 9. Saturday, October 24
Monday, October 26 – Saturday, October 31
Work on Saturday, October 31 will end at 2:00 PM (ahead of Trick-or-Treating from 4:00 PM – 7:00 PM) Please use caution when traveling through the work zone, follow all traffic control personnel and signage, and allow additional travel time. For the latest construction updates, maps, and project information, visit lakebluff.org. |
|
Green Bay Road Reconstruction. This project should be nearing completion within the next 30 days. Saturday, October 17
Monday, October 19 – Saturday, October 24
Looking Ahead: Week of October 26 Paving asphalt for the road and driveways. Please use caution when traveling through the work zone, follow all traffic control personnel and signage, and allow additional travel time. For the latest construction updates, maps, and project information, visit lakebluff.org.
|
Green Bay Road Construction Update: 10/16/2026
- Details
|
Green Bay Road Reconstruction. This project should be nearing completion within the next 30 days. Saturday, October 17
Monday, October 19 – Saturday, October 24
Looking Ahead: Week of October 26 Paving asphalt for the road and driveways. Please use caution when traveling through the work zone, follow all traffic control personnel and signage, and allow additional travel time. For the latest construction updates, maps, and project information, visit lakebluff.org. |

Green Bay Road Construction Update: 9/26/2026
- Details
Green Bay Road Construction Update from the Village of Lake Bluff.
Saturday, September 26
- Storm sewer underdrains and various connections will be completed on Green Bay Road from West Hawthorne Court to Birkdale Road. The road will be closed at each location as the work progresses from south to north.
Monday, September 28 – Friday, October 2
- Preparation for concrete work will begin on Green Bay Road from West Center Avenue to West Hawthorne Court. That includes grading and compacting the aggregate base and setup for pouring concrete the following week.
Looking Ahead: Week of October 5
Pouring concrete for curb and gutter, sidewalk and driveway aprons on the west side of Green Bay Road from West Center Avenue to West Hawthorne Court.
Please use caution when traveling through the work zone, follow all traffic control personnel and signage, and allow additional travel time.
For the latest construction updates, maps, and project information, visit lakebluff.org.

GREEN BAY ROAD CONSTRUCTION UPDATE 9/18
- Details
|
Green Bay Road Reconstruction: Saturday, September 19
Monday, September 21 – Friday, September 25
Please use caution when traveling through the work zone, follow all traffic control personnel and signage, and allow additional travel time. |

Green Bay Road Construction Update: 9/11/2026
- Details
Green Bay Road Reconstruction:
Saturday, September 12
- Storm sewer crossings will be installed on Green Bay Road between West Center Avenue and West Prospect Avenue. The road will be closed at each location as the work progresses from north to south.
Monday, September 14 – Saturday, September 19
- Storm sewer installation will continue on Green Bay Road from West Prospect Avenue to the south. The road will be closed one block at a time as the work progresses south, ending at West Hawthorne Court.
Looking Ahead: Week of September 21
Finish storm sewer installation and start preparing for curb and gutter work on Green Bay Road from West Center Avenue to West Hawthorne Court.
Please use caution when traveling through the work zone, follow all traffic control personnel and signage, and allow additional travel time.
For the latest construction updates, maps, and project information, visit lakebluff.org.

Green Bay Road Construction Update: 9/04/2026
- Details
|

Green Bay Road Construction Update: 8/28/2026
- Details
Green Bay Road Reconstruction: Good News! There will be no construction on Saturday, August 29.
Monday, August 31 – Friday, September 4
- Storm sewer installation will continue on Green Bay Road from West Center Avenue to the south. This work is expected to take two weeks. The road will be closed one block at a time as the work progresses south, ending at West Hawthorne Court.
- West Center Avenue will be closed on Monday, August 31 to complete the storm sewer work at that location. Residents should use Thornwood Lane to access IL Route 176.
Saturday, September 5 – Monday, September 7
- There will be no construction over the Labor Day weekend.
Looking Ahead: Week of September 8
Storm sewer installation will continue.
Please use caution when traveling through the work zone, follow all traffic control personnel and signage, and allow additional travel time.
For the latest construction updates, maps, and project information, visit lakebluff.org.

Green Bay Road Construction Update: 8/21/26
- Details
Good News: There will be no construction on Saturday, August 22.
Monday, August 24 – Wednesday, August 26
- Final grading of the road base will continue.
- Asphalt paving will start on Tuesday, August 25 at the south end of the project from West Hawthorne Court to south of West Witchwood Lane, followed by the north end of the project from West Center Avenue to IL Route 176, being completed by end of day on Wednesday, August 26.
- Work at the south end of the project will require a full closure of Green Bay Road. Residents north of the Green Bay Road bridge should access their homes from the north via IL Route 176. Residents south of the bridge should access their homes from the south through Lake Forest.
- Work at the north end of the project will have flaggers to direct traffic through the work zone. Expect delays as traffic patterns change as the work progresses. If exiting north to IL Route 176, it is recommended to turn onto Green Bay Road from West Sheridan Place (from the east or west) or West Prospect Avenue (from the west) as crews will be busy paving on Green Bay Road at West Center Avenue and Thornwood Lane.
Thursday, August 27 – Friday, August 28
- Storm sewer installation will continue on Green Bay Road from West Center Avenue to the south. The road will be closed one block at a time as the work progress south, ending at West Hawthorne Court.
Saturday, August 29
- Reserved as a weather or schedule recovery day, if needed.
Looking Ahead: Week of August 31
Storm sewer installation will continue on Green Bay Road.
Please use caution when traveling through the work zone, follow all traffic control personnel and signage, and allow additional travel time.
For the latest construction updates, maps, and project information, visit lakebluff.org.

Green Bay Road Construction Update: 8/14/26
- Details
Green Bay Road Reconstruction Updates
There is no road construction scheduled for Saturday, August 15. As for next week...
Monday, August 17 – Friday, August 21
- Concrete work will be completed and the road base prepared for asphalt paving on the south end of the project from West Hawthorne Court to south of West Witchwood Lane. This will require a full closure of Green Bay Road.
- Our residents north of the Green Bay Road bridge should access their homes from the north via IL Route 176.
- Our residents south of the bridge should access their homes from the south through Lake Forest.
- The road base will also be prepared for asphalt paving on the north end of the project from West Center Avenue to IL Route 176, but is not expected to significantly impact traffic.
Saturday, August 22
- This is reserved as a weather or schedule recovery day, if needed.
Looking Ahead: August 24-26
Asphalt paving is scheduled on the north and south ends of the project.
Please use caution when traveling through the work zone, follow all traffic control personnel and signage, and allow additional travel time.
Visit lakebluff.org for the latest construction updates, maps, and project information.

Green Bay Road Construction Update: 8/7/26
- Details
This is an important Green Bay Road Construction Update from the Village of Lake Bluff.
Good News: There will be no construction on Saturday, August 8.
Monday, August 10
- Weather dependent, concrete sidewalk will be finished on the north end of the project and formwork will be cleaned up. This is not expected to significantly impact traffic.
Monday, August 10 – Friday, August 14
- Concrete work will begin on the south end of the project from West Hawthorne Court to south of West Witchwood Lane which will require a full closure of Green Bay Road.
- Residents north of the Green Bay Road bridge should access their homes from the north via IL Route 176.
- Residents south of the bridge should access their homes from the south through Lake Forest.
Saturday, August 15
- Reserved as a weather or schedule recovery day, if needed.
Looking Ahead: August 17–21
Work will continue on the north and south ends of the project to prepare for asphalt paving.
Please use caution when traveling through the work zone, follow all traffic control personnel and signage, and allow additional travel time.
For the latest construction updates, maps, and project information, visit lakebluff.org.
Green Bay Road Closures: Week of 8/3
- Details
Green Bay Road Construction Update from the Village of Lake Bluff – Friday, July 31, 2026
Good News: There will be no construction on Saturday, August 1.
Monday, August 3
- Green Bay Road at Thornwood Lane will be reduced to one lane throughout the day while crews complete storm sewer work.
- Traffic control personnel will be on-site to direct traffic safely.
Tuesday, August 4
- Storm sewer work will begin at West Hawthorne Court and move south toward West Witchwood Lane. Green Bay Road will be closed in the active work area.
- West Witchwood Lane will remain open on Tuesday, allowing residents to access their homes from either the north (IL Route 176) or the south (Lake Forest).
- Concrete work will also begin on the north end of the project. This work is not expected to significantly impact traffic.
Wednesday, August 5 – Friday, August 7
- Storm sewer work will shift to West Witchwood Lane, requiring a full closure of Green Bay Road at Witchwood Lane.
- Residents north of the Green Bay Road bridge should access their homes from the north via IL Route 176.
- Residents south of the bridge should access their homes from the south through Lake Forest.
- Concrete work will continue on the north end of the project. Traffic control personnel will remain on-site throughout the work zone.
Saturday, August 8
- Reserved as a weather or schedule recovery day, if needed.
Looking Ahead: August 10–14
Take note: concrete work on the south end of the project will require a full closure of Green Bay Road. During this period, all residents must access their homes from the north via IL Route 176. Access from the south through Lake Forest will not be available.
Please use caution when traveling through the work zone, follow all traffic control personnel and signage, and allow additional travel time.
For the latest construction updates, maps, and project information, visit lakebluff.org.

Green Bay Road Closures - 7/28 Updates
- Details
Green Bay Road Construction Update
Good news! Water system work finished ahead of schedule, allowing storm sewer work to begin tomorrow.
- On Wednesday, July 29 Green Bay Road at Thornwood Lane will be reduced to one lane with flaggers directing traffic.
- On Thursday, July 30 and Friday, July 31 Green Bay Road will be closed from Park Lane to West Hawthorne Court. Residents should use West Witchwood Lane for access.
- On Saturday, August 1 (anticipated): Work at West Witchwood Lane will require a full closure. Residents should plan to access their homes from the south (via Lake Forest). Additional details will be provided.
Please use caution in the work zone and allow extra travel time. Thank you for your patience as we complete these infrastructure improvements.

Green Bay Road Closures: 7/27- 7/31
- Details

On Monday, July 27, the intersection of Green Bay Road and Thornwood Lane will be closed all day.
On Tuesday, July 28, Green Bay Road closed from West Witchwood Lane to West Hawthorne Court all day.
On Wednesday, July 29 Green Bay Road closed from West Witchwood Lane to Park Lane will be closed all day.
On Thursday, July 30, and Friday, July 31, the intersection of Green Bay Road and Thornwood Lane will be closed.
Traffic control personnel will be on-site throughout construction.
Please use caution in the work zone and allow extra travel time.
Thank you for your patience and cooperation as we complete these important infrastructure improvements.
Green Bay Road Closures: 7/24 Weekend Map
- Details

Green Bay Road Closures: Week of 7/20
- Details
On Monday, July 20, and Tuesday, July 21, the intersection of Green Bay Road and West Center Avenue will be closed. Residents traveling to Green Bay Road from the north should use Thornwood Lane as an alternate route.
On Wednesday, July 22, Green Bay Road will be closed at Illinois Route 176. Residents of the East and West Terrace neighborhoods must access their homes from the south by traveling through Lake Forest. Normal access is expected to be restored by approximately 7:00 p.m. that evening.
Traffic control personnel will be on-site throughout construction. Please follow all posted signs and flagger directions, use caution in the work zone, and allow extra travel time.
Residents in the affected area will receive additional updates via Smart 911 notification. If you have not already, please register for notifications at https://www.lakebluff.org/departments-services/police-department/1113-smart911
Thank you for your patience and cooperation as we complete these important infrastructure improvements.

[GREEN BAY ROAD] Updated Map: 7/10
- Details

Looking Ahead – We anticipate the most disruptive construction activity will take place from July 20 to August 21. During this time, the contractor will be installing new storm sewer pipes, curbs and gutter, and rebuilding the road. Residents along Green Bay should anticipate parking on side streets during portions of this period. Traffic patterns and access will change frequently for all residents living in the East and West Terrace Subdivisions. Please refer to the Village’s website for the latest updates. The Village will continue to use Smart 911 (Reverse 9-1-1) to provide closure updates as soon as practicable.